Wreck removal consultancy

Salvage and Wreck removal consultancy

In the summer of 2015 MASS consulted during the tender phases of the mv ‘SEWOL’ in Korea for Mammoet Salvage.

In fall of 2015 MASS was involved in composing of a robust salvage and wreck removal plan during the tender phase of the wreck removal of the fishing vessel ‘Fong Kuo 869’ off the coast of Taiwan.

FPSO Field Installation

FPSO Enquest Producer Field Installation and Hook-Up

During the installation of the EnQuest Producer in the Alma-Galia field in spring of 2015, MASS was involved in connecting of the 9 pre-laid moorings to the turret of the FPSO. The AHT ‘Normand Progress’ picked up the moorings from seabed by means of ROV and succesfully connected the 9 moorings as per planned procedure to the fore runner chains, deployed from FPSO.

MASS supervised all operations on board the AHT ‘Normand Progress’ and made sure all necessary information was relayed to the Boskalis Marine Operations representaive on board the FPSO.